Full Change Requests
Raise a Change Request on the full Change Request page, work through its reference documents by allocating new drawings and sheets or linking existing ones, and manage its folders, comments, and favourites.
Overview
The full Change Request page is Lunr's newer Change Request experience. It replaces the creation dialog with a full page, and adds an Overview tab, a Reference Documents tab, and a workflow progress nav across the top of the request.
This page covers the full experience from end to end. If your organisation gives you the standard Change Request instead, see Standard Change Requests. Introduction to Change Requests explains which one you have and how the two differ.
Change Requests are listed on a project's Change Requests tab, described in Working in a Project.
Raising a Change Request
Select New Change Request in the Action Pane of a project's Change Requests tab, which opens the creation page.
You can also raise one from the Create menu, including from the repository. Raising a request outside a project asks you to choose the project it belongs to, so you do not have to open the project first.
The page captures more than a subject and a message. Alongside those it takes attachments, tags, a priority and due date where those are enabled, and the reference documents the request asks for, and it can nominate a reviewer for each workflow stage. It can also attach checklists and add documents by drawing number, and a document tracking grid lists the documents the request covers. Where priorities are enabled, a priority is required. Where your workflow needs authorisation, choose an Authoriser, then select Submit for Authorisation, or Save as Draft to come back to it. Otherwise the button reads Create Change Request, with a chip beside it reading "Ready to submit" or naming the field that is still required. Everything on it can be edited afterwards, so nothing has to be final before you create the request.
Where your organisation has set them up, the page also guides what you enter:
- The empty Message box can show guidance text on what to include. The text is only a hint and is never saved as your message.
- Choosing a priority fills in the Due Date for you, counting the priority's turnaround from today, and a note beneath it shows the turnaround, for example "P2: 7 days turnaround". Depending on your organisation, the due date is either fixed by the priority or one you can change. Change the date yourself and the note disappears, since it no longer describes your date. Choose the priority again to restore its date and note.
- Where the priority list includes a Low option, a due date later than the longest turnaround of the other priorities changes the priority to Low. Bring the date back within those turnarounds and the priority you chose before returns. The same applies when you edit the due date on an existing request.
- Required fields carry a marker. A field that is missing turns its card amber with a hint, either "Required" or "Priority or Due Date required", and you cannot create the request until you complete it. A message lists what is missing, for example "Priority or Due Date is required".
- Where your organisation asks for a priority or a due date rather than always a priority, either one is enough. The page asks for "Priority or Due Date" until you enter one of them, and then clears both hints. When you edit the details of an existing request, both fields carry an asterisk, and Save is held back with "Enter a priority or a due date." while both are empty.
- Date tags offer a date picker, so you choose a date rather than typing it.
Assigning Documents to a Change Request
Documents reach a Change Request in four ways.
- Select them before raising the request.
- Add them as reference documents, covered in Reference Documents below.
- Upload them into the request. On the Documents tab, drag files onto the page, or use the Create menu in the Action Pane to create a document in the request. The same name-matching rules apply here as anywhere else, so an upload matching a document already in the request replaces its content, covered in Uploading Documents.
- Assign existing documents to it. Select the documents anywhere in the repository or a project, then select Assign to Change Request in the More menu.
Assign to Change Request opens a dialog naming the documents you selected. Choose the project under Assign to project, then the request under Assign to Change Request. Leave the Change Request field empty, or enter a subject that matches no existing request, and Lunr creates a request with that subject and assigns the documents to it. The dialog confirms which of the two will happen before you submit, and warns you when a document already has child documents, since proceeding creates concurrent versions of it.
Assign to Change Request is unavailable while only folders are selected. If you cannot add documents to the request you chose, a notification reads "You do not have permission to add documents to this change request."
Working a Change Request
A full Change Request opens on its Overview tab, which carries the request's details and its message. Documents, Comments, History, and Reference Documents sit alongside it in that order, and Checklist joins them where checklists are enabled. The Documents, Comments, and Reference Documents tabs show a count.
The header carries the request's status badge, an On Hold badge where it applies, and who opened the request and when, above a breadcrumb back to the project and its Change Requests list. Below it, the workflow progress nav shows the statuses the request passes through and how far along it is.
| Action | What it does |
|---|---|
| Create | Creates a document directly in the request. |
| Request Workflow | Moves the request to its next status. It appears only where you have an action available. From the starting status, the request's creator, assignee, reviewers, and project manager can move it on. From any later status, only its reviewers can, and a request that is cancelled has no actions. A request that is complete can be moved on only by a document controller. People allowed to manage projects can take these actions whatever their role in the request. A request with validation issues offers no actions until they are resolved. If you are refused, the message reads "You don't have permission to perform this transition." |
| Place on hold, Update hold, and Resume | Reviewers can pause a request awaiting external input, change the hold, and pick the request up again, where your organisation has Change Request holds enabled. Place on hold and Update hold are hidden once the request is Complete or Cancelled, and Resume appears only while the request is on hold. |
| Release All or Release Selected | Releases the request's valid documents, all of them or only those you have selected. It is for document controllers and appears only where your organisation allows bulk release, and it is hidden once the request is Complete or Cancelled. |
| Download Package | Downloads the request's documents as a package, or only your selection where documents are selected. Where your organisation offers package options, a dialog lets you choose what to include, such as natives, renditions, the Change Request summary sheet, attachments, annotations, and xrefs. |
| Generate CR Summary | Opens a dialog of options, then exports a PDF summary of the request. |
| Share Folder | Shares a Change Request folder. It needs Change Request folders enabled and is limited to people allowed to manage projects, and stays greyed out until a folder is selected. |
Assigned To and Reviewers sit below, each listing the people currently on the request and reading "None yet" until someone is set. A control beside each heading reassigns the request or its reviewers if you are allowed to reassign work, or are the assignee or one of the reviewers.
Where a workflow transition nominates its own reviewers, a Select Reviewer field appears for each one, offering the users eligible for that step alongside a Vendor option. A transition can mark its reviewer as required, shown by a red asterisk beside the field. A required field cannot be cleared, and leaving it empty reads "A reviewer must be selected." and holds the request until you choose someone. Where a step draws its reviewers from more than one user group, it has a single field, labelled with all of the group names, listing everyone in those groups once, so you choose one reviewer for the step.
Some Request Workflow actions ask who should review the request next, under Reviewer selection, which counts the people selected. Where the next status takes its reviewers from a user group, the list offers that group's members and starts empty, and Submit stays unavailable until you pick someone. Otherwise it starts with the request's current reviewers.
Where the request is linked to a project folder, a Project Folder entry beneath the reviewers shows where that folder sits in the project. A path more than three folders deep shows only its first and last folders, and pointing at it shows the full path. People allowed to manage projects can select Project Folder in the Action Pane to link the request to a different folder.
Selecting documents in the list switches the lower part of the panel to batch actions covering the selection, including updating tags, transitioning documents through their own workflow, sharing, exporting, and Discard from CR.
Reference Documents
The Reference Documents page lists the changes the request asks for. Each line carries a change type, which decides how the line is processed. Working a request means processing those lines until every change has either produced a new document or been linked to an existing one.
| Change type | What it asks for | How it is processed |
|---|---|---|
| NEW DWG | A new drawing | Allocation |
| NEW SHT | New sheets on a drawing | Allocation |
| NEW DWG+SHT | A new drawing and its sheets | Allocation |
| REVISION | A new revision of an existing drawing | Child linking |
| SUPERSEDE | An existing drawing superseded | Child linking |
| OBSOLETE | An existing drawing made obsolete | Child linking |
Lines that raise something new are processed by allocating a document from a repository template. Lines that act on a drawing already in the repository are processed by linking a child document to it.
A NEW SHT line adds sheets to a drawing that already exists, so it must be linked to that drawing. Enter the drawing number in the line's Drawing Number field and pick the drawing from the list of results, which shows each result's number, file name, and title. A linked line shows a link icon in the field. An unlinked line shows a red unlink icon, and its tooltip reads "Not linked. Pick a drawing from the list." Outside edit mode, an unlinked line carries a Not linked badge.
Text you type over a linked line's number is not saved. Leave the field or press Esc and the linked number returns. To link the line to a different drawing, pick another result from the list. Clearing a line's link also clears its revision.
On the creation page, an unlinked NEW SHT line stops you creating the request, and the chip beside the button reads, for example, "Link a drawing on line 2 to submit". Select the chip to go to that line.
The toolbar offers Edit, Reset Processed (Reset Selected with a count when lines are selected), Link Docs (Link Selected with a count), Bulk Allocate, and an export. On a row, Process and Link are icon buttons, with the tooltips "Process this line" and "Link the child document for this line". Bulk Allocate is hidden while you are editing and when no line is ready for allocation.
Documents already in the repository are added as reference documents by selecting them, then choosing Add as CR reference docs in the More menu and picking the Change Request in the dialog that opens. The entry is offered only on the full experience, and only when you have selected documents and not only folders.
Once a request is authorised, its recipients hear about new reference documents in one consolidated notification, sent when you save, rather than one email for each line. The same notification covers edits to existing lines, such as a change to the sheet count, which reads "N sheets added" or "N sheets removed", and any other edited field is listed with its old and new value. Lines you add and then abandon without saving send nothing.
Allocating New Drawings and Sheets
Select Bulk Allocate in the toolbar to allocate every line waiting for allocation in one action, rather than working through them one at a time. To allocate a single line instead, select Process on that row.
Both routes open the same Bulk Allocate Reference Documents dialog, which works in two steps.
- Under Configuration, choose the Template the placeholder documents are created from. This is required. Optionally choose a Target Folder, which uses the same coloured folder picker as moving documents, covered under Moving to a Change Request Folder. It starts on Change request root. Leave it there to add the documents outside any folder.
- Check the lines under Documents to Allocate and anything reported under Tag Requirements. Where a line is missing a tag it needs, select the edit action on that line to supply it.
- Select Preview to open the Preview & Confirm step, which shows exactly what the allocation will produce.
- Check the lines and their document numbers, covered in Checking the Preview below.
- Select the allocate button, which names the count, for example Allocate 11 Documents, or select Back to change the configuration first. The button reads "Allocating..." while it runs.
Lunr reports what it allocated when the run finishes, including any lines it skipped because they were already allocated.
Checking the Preview
The top of the Preview & Confirm step states the outcome, for example "11 documents will be created", or the reason nothing will be created yet, above the template in use. Lines are grouped under Needs Attention, New Sheets, and New Drawings. Each line names its change type and drawing, and lists under Creates the exact document numbers it will produce. A long list shows the first six, with Show All to see the rest.
New sheets start at the first drawing revision, for example A, rather than taking the revision of the sheet they are modelled on, and a revision at the end of the file name is replaced in the same way.
A line that cannot be allocated is listed under Needs Attention with the reason. For example, a NEW SHT line whose drawing cannot be found reads "No existing drawing was found for" the number, followed by "Edit the line and pick the drawing from the list, then allocate again." Select Skip This Line to leave the line out of this allocation, or Undo to bring skipped lines back. Nothing is allocated until every line in Needs Attention is fixed or skipped.
Choosing Starting Sheet Numbers
Where a line adds sheets to a drawing, it is listed under New Sheets with the drawing's next available sheet number in its Starting Sheet field. Creates lists the sheet numbers the line will produce, with any number that clashes with an existing sheet, or that two lines both ask for, shown in red.
To start a line somewhere else, enter a different number in its Starting Sheet field, and the preview updates. Where the drawing has unused numbers between its existing sheets, they are listed under Or start at, which offers only starting numbers where the whole run of sheets fits; select one to start the line there. Select Use Next Available, which shows the number it returns to, to go back to the line's next available number.
The allocate button stays unavailable while any line has a clash or an invalid starting sheet, or while the preview is updating, and pointing at it explains why. The starting sheet applies to this allocation only and is not saved against the line.
Allocating a reference document releases the new document as a master, so it requires both document controller standing and reviewer standing on this Change Request. Bulk Allocate does not appear without them.
Partly Allocated Lines
A line asking for a batch of sheets can be allocated more than once. A row shows how many of its requested sheets have been allocated, as a fraction, and an already-allocated sheet title can no longer be changed.
Raising a line's quantity after it has been allocated brings it back into the list, so a later run allocates only the extra sheets rather than repeating the ones already done.
Linking Existing Drawings
A REVISION, SUPERSEDE, or OBSOLETE line is processed by linking a child document to the repository drawing it names, so the line cannot be processed until that drawing has been chosen.
When you link REVISION lines whose drawings have xrefs, using Link on a row or Link Docs or Link Selected in the toolbar, the Revise XRefs? dialog asks which xrefs to revise with them. Each xref has a box, and all are selected to begin with. Linking several drawings groups the xrefs under each drawing, and an xref shared by two drawings has one box.
- An xref already being linked in this run reads "Already being linked", and stays selected.
- An xref that already has an unlinked REVISION line reads "On this change request". Selecting it adds that line to the run rather than a second line.
- An xref on the request in any other way reads "Already on this change request" and cannot be selected. Where you cannot add lines to the request, new xrefs cannot be selected either, and pointing at the box explains why.
Select Link Documents to add each selected xref as a REVISION line and link it in the same run, Skip XRefs to link only the drawings, or Cancel to link nothing. A new xref line takes the file name as its drawing number and leaves the revision blank. Once the request is authorised, the added lines are covered by one consolidated notification.
Linking requires involvement in this Change Request as its creator, its assignee, one of its reviewers, or the manager of its project. People allowed to manage projects can do it regardless of involvement.
Change Request Folders
Where your organisation enables Change Request folders, a request can hold folders of its own.
A Change Request folder starts closed, visible only to the members assigned to it rather than to everyone on the request. This is the opposite of a project folder, which starts open, so check folder membership if you expect the whole request to see a folder's documents.
Comments
Anyone who can open a Change Request can comment on it. You do not need to be its creator, its assignee, or one of its reviewers. A comment can be resolved by its author or by users allowed to resolve any comment.
Favourites
Select the star on a Change Request row to favourite it, and it appears in your favourites for quick access. The Favourite Change Requests tile on the Change Request Dashboard lists them, as does the same tile at the top of a project, which shows only that project's favourites. The tile shows your first eight favourites, with a count of all of them beside its heading. Select Show N More, where N is the number of hidden favourites, to see the rest, and Show Fewer to collapse the list again. A request that reaches Complete or Cancelled drops out of your favourites list, though its star still shows on the request's own page so you can clear it. A rejected request stays in the list, since it can be updated and resubmitted.
Finding Change Requests
The Change Requests tab offers a search field, a Filter button, an "Open | Closed" summary, an Export button, and a Sort dropdown. A rejected request counts as closed here and in the export, matching the Change Request Dashboard. The filters cover the assignee and your Change Request tags. To see only the documents that have validation issues, use the Validation issues toggle on a request's Documents tab. Each row shows the request's number, its status and On Hold badges, and a preview of its message. Some users can delete a request from the list.
Standard Change Requests
Raise a standard Change Request from the Create Change Request dialog, gather the documents it covers, and work it through review to release, using its Documents, Comments, and History tabs.
Document Workflows
Move a document through its workflow, read its status badge, take part in reviews, and see why a workflow action might be unavailable.